1) Which type of survey is used for the location of the road involved stake out the final central line by continuous transit survey and detailed levelling?
Maps study
Reconnaissance survey
Preliminary survey
Final survey
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Final survey
Question Details
1) Which type of survey is used for the location of the road involved stake out the final central line by continuous transit survey and detailed levelling?
Maps study
Reconnaissance survey
Preliminary survey
Final survey
2) What is the rate of rise or falls along the length of the road with respect to the horizontal length?
Road way
Gradient
Level difference
contour interval
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Gradient
Question Details
2) What is the rate of rise or falls along the length of the road with respect to the horizontal length?
Road way
Gradient
Level difference
contour interval
3) In which year the Nagpur plan conference was held?
1941
1942
1943
1947
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 1942
Question Details
3) In which year the Nagpur plan conference was held?
1941
1942
1943
1947
4) What is road way width as per IRC for national and state highway?
12 M
10 M
8 M
7.5 M
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 12 M
Question Details
4) What is road way width as per IRC for national and state highway?
12 M
10 M
8 M
7.5 M
5) What is road way width as per IRC major district road?
12 M
10 M
8 M
7.5 M
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 10 M
Question Details
5) What is road way width as per IRC major district road?
12 M
10 M
8 M
7.5 M