ESTIMATION AND COSTING OF WIRING - Practice Mode
1) What is the first step taken during preparation of estimating the material required for any type of wiring installation?
Correct Answer: Take the lay out
2) Which load is to be connected from stand by generator set in the event of failure of mains?
Correct Answer: Fire lift and water pumps
3) Which is the recommended height of energy meter to be installed from floor level in commercial wiring as per IE rule?
Correct Answer: Not less than 1m
4) Which is to be considered before the selection of conductor, protective devices and switch gear in commercial wiring?
Correct Answer: Diversity factor
5) Where the location of main switch in a domestic wiring installation?
Correct Answer: Near to termination of service line