ESTIMATION - Practice Mode

1) What is the unit for excavation in M.K.S system?
Correct Answer: cu.m
2) What is the minimum cubical quantity for bill quantity calculation?
Correct Answer: 0.01 m<sup>3</sup>
3) What is the unit for cement concrete in M.K.S. system?
Correct Answer: cu.m
4) What is the unit for brick work in cement mortar for superstructure in MKS system?
Correct Answer: cu.m
5) What is the unit for steel reinforcement bars etc in RCC, RB work in MKS system?
Correct Answer: Quintal