1) Which estimate is prepared while the expenditure on a work exceeds by more than 10%?
Supplementary
Revised
Annual repair
Cubical content
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Revised
Question Details
1) Which estimate is prepared while the expenditure on a work exceeds by more than 10%?
Supplementary
Revised
Annual repair
Cubical content
2) Which estimate is prepared while the original sanctioned estimate is exceeded by more than 5%?
Supplementary
Extension and improvement
Revised
Plinth area
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Revised
Question Details
2) Which estimate is prepared while the original sanctioned estimate is exceeded by more than 5%?
Supplementary
Extension and improvement
Revised
Plinth area
3) Which estimate is required for administrative sanction?
Approximate
Detailed
Revised
Supplementary
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Approximate
Question Details
3) Which estimate is required for administrative sanction?
Approximate
Detailed
Revised
Supplementary
4) How aggregate is specified?
Size in mm
Length in mm
Height and breadth in cm
Length in m, section in mm
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: Size in mm
Question Details
4) How aggregate is specified?
Size in mm
Length in mm
Height and breadth in cm
Length in m, section in mm
5) Which brick wall thickness is measured in sq.m?
10 cm
15 cm
20 cm
30 cm
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 10 cm
Question Details
5) Which brick wall thickness is measured in sq.m?
10 cm
15 cm
20 cm
30 cm