RATE ANALYSIS - Practice Mode
Categories
Draughtsman (Civil)
RATE ANALYSIS
Practice Mode
1) What is the out-turn of mason constructing stone arch work?
0.40 cu.m
0.55 cu.m
0.80 cu.m
0.90 cu.m
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 0.40 cu.m
Question Details
1) What is the out-turn of mason constructing stone arch work?
0.40 cu.m
0.55 cu.m
0.80 cu.m
0.90 cu.m
2) What is the out-turn of mason, constructing superstructure with brick masonry?
0.55 cu.m
0.85 cu.m
1.00 cu.m
1.25 cu.m
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 1.00 cu.m
Question Details
2) What is the out-turn of mason, constructing superstructure with brick masonry?
0.55 cu.m
0.85 cu.m
1.00 cu.m
1.25 cu.m
3) What percentage contractors profit is included in the analysis of rate?
5
10
15
20
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 10
Question Details
3) What percentage contractors profit is included in the analysis of rate?
5
10
15
20
4) What quantity bitumen is required for 100m
2
first coat painting on DPC?
75 kg
100 kg
125 kg
150 kg
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 150 kg
Question Details
4) What quantity bitumen is required for 100m<sup>2</sup> first coat painting on DPC?
75 kg
100 kg
125 kg
150 kg
5) What quantity of stone is required for 1m
3
of rubble masonary?
0.5 cu.m
0.75 cu.m
1.00 cu.m
1.25 cu.m
Show Answer
Report Question
What's wrong with this question?
Report
Correct Answer: 1.25 cu.m
Question Details
5) What quantity of stone is required for 1m<sup>3</sup> of rubble masonary?
0.5 cu.m
0.75 cu.m
1.00 cu.m
1.25 cu.m