Multiple Choice Question (MCQ)
Question: What procedure is to be followed for welding pipes under 6G position?
A.
Pipe not rotated weld vertical
B.
Rotate pipe and deposit weld vertical
C.
Pipe not rotated weld deposit horizontal
D.
Pipe not rotated and pipe axis 45 Degree angle deposit weld flat, vertical
Correct Answer: Pipe not rotated and pipe axis 45 Degree angle deposit weld flat, vertical